2ZR-FE STARTING ENGINE SWITCH INSTALLATION
PROCEDURE
89611
1.INSTALL ENGINE SWITCH
a.
Engage the 2 claws to install the engine switch to the No. 2 switch hole base.
55447C
2.INSTALL NO.2 SWITCH HOLE BASE
55545
3.INSTALL FUSE BOX OPENING COVER
55410C
4.INSTALL INSTRUMENT CLUSTER FINISH PANEL ASSEMBLY
55405B
5.INSTALL CENTER INSTRUMENT CLUSTER FINISH PANEL SUB-ASSEMBLY
55404E
6.INSTALL UPPER INSTRUMENT CLUSTER FINISH PANEL SUB-ASSEMBLY
55317A
7.INSTALL INSTRUMENT SIDE PANEL RH
55435B
8.INSTALL NO.1 METER HOOD CLUSTER